The planned four-hour window at Site North on 12 July (02:00–06:00 local) is complete. It covered the annual inspection of the hydro power feed with the utility and the replacement of the intake air filters across all racks.
Why the night
Planned work is scheduled for the lowest-load hours of the site's grid, and always announced in the Telegram channel at least 48 hours ahead. Reserve hash power covered the window, so daily rewards for plans were unaffected.
Numbers
780 machines back at nameplate by 05:40. Intake filters: 64 replaced. Hash boards found faulty during the inspection: 6, all swapped from on-site stock.
The next planned window at Site North is the Q4 replacement of the remaining S19-class units; dates will be posted here.