Eight months after Site East went live, the second hall is under way. The concrete slab was poured on 14 September; the steel frame goes up over the next three weeks and the first of twenty immersion tanks is scheduled to arrive in the second week of October.
What is going in
The hall is designed for 320 Whatsminer M66 units in single-phase immersion, the same configuration that has been running in Hall 1 since March. At nameplate that is roughly 0.5 PH/s of additional hash power at an efficiency around 18.5 J/TH, cooled by dielectric fluid and dry coolers on the roof - no water use.
Power
Power comes from the same mix as Hall 1: the on-site solar array during the day and the regional grid at night, under a contract that lets the operator curtail us in peak hours in exchange for a lower rate. Expect the site's overall uptime to sit slightly below Site North's during the summer months for that reason - the fleet page will show it.
What it means for plans
New capacity goes on sale in tranches once machines are hashing, never before. When the first tanks are online we will announce it here and in the Telegram channel, and the fleet table on the mining-hardware page will list the new units the same day.
